Dudy Noble Field
Jackson Precast

 
Dudy Noble Field Project.png
 

Location:
MSU
Starkville, MS 39759

Schedule:
Project Start Date: 2017
Precast Completion in Plant: 11/2017
Precast Erection Start Date: 03/2018
Precast Erection Completion Date 06/2018
Project Completion Date: 2019

Cost:
Total Project Cost: $55 million

Involved Companies

Precast Concrete Producer

Jackson Precast
3325 Lawson St
Jackson, MS 39213
https://www.jpi.ms/

Architect

Wier Boerner Allin Architecture
2727 Old Canton Road, Suite 200
Jackson, MS 39216
https://wbaarchitecture.com/

Installer

Bracken Construction
725 Avington Drive
Ridgeland, MS 39157
http://www.brackenconstruction.com/

General Contractor

Jesco, Inc
2020 Mccullough Blvd
Tupelo, MS 38801
http://www.jescoinc.net/

 
 
 

Background

Built in the 1980s, MSU’s Dudy Noble Field was in need of modern renovations. The project consisted of the main entrance sign panel that patrons could walk under to access the field, along with white limestone mimicked panels at the entrance and ticket booth.  The left field and right field stair tower exteriors were made of architectural precast concrete wall panels with thin-set brick as well.

Jackson Precast provided 99 panels covering almost 8,000 SF with architectural precast concrete using an acid-etched finish to mimic white limestone. Thin-set brick, provided by Columbus Brick of Mississippi, was incorporated into the wall panels.

The renovation opened up before the first game this Spring of 2019.


MSU has construction cameras that allowed viewers to watch the construction in process. Below are a few videos that show the construction and highlight the precast elements Jackson precast contributed.