Erato Street Cruise Terminal/Parking Structure
Tindall

 
Erato Street.png
 

 Location:

Port of New Orleans
New Orleans, LA

Schedule:
Project Completion Date: 2006

Cost:
Total Project Cost: $36 million
Square Footage: 367,054 SF

Involved Companies

Precast Concrete Producer

Tindall
11450 Saracennia Road
Moss Point, MS 39562
https://tindallcorp.com/

Architect

CH2M Hill (now Jacobs Engineering)
1999 Bryan Street, Suite 1200
Dallas, TX 75201
https://www.jacobs.com/

Engineer of Record

Morphy Makofsky Incorporated Consulting Engineers
336 N. Jefferson Davis Pkwy
New Orleans, LA 70119
https://www.mmi-eng.com/

General Contractor

Broadmoor Construction
2740 N Arnoult Rd
Metairie, LA 70002
http://www.broadmoorllc.com/

 

Background


At first, a tight deadline was the serious challenge facing the Erato Street Cruise Terminal and Parking Structure construction. Then, Hurricane Katrina devastated the Gulf Coast. Despite 120-mph winds, ten inches of rain, and 20-foot storm surges, the previously erected members of the structure suffered no damage. Afterward, the rapid precast schedule allowed Tindall to complete erection with only a four-month delay. Despite the unforeseen interruption in construction, the project budget was unaffected. Tindall’s engineering, delivery, and erection teams faced some of the most complex challenges during this build.

When Hurricane Katrina hit the Gulf Coast, the previously erected precast members sustained no damage. However, Tindall still faced the serious challenge of reevaluating the project schedule after the storm. This 367,054-square-foot elevated precast, prestressed concrete structure’s fast-track construction schedule was accelerated by dividing the design into three phases. Tindall was able to maintain the revised schedule by changing erection sequence mid-project to coordinate with foundation work.

The six-story terminal/garage efficiently handles drop-offs, baggage, and customs on the ground level. Ticketing, waiting areas, and the cruise liner gangway appear on the second floor, and approximately 1,000 vehicle stalls make up the top four floors. The 1,800 precast pieces used for this project included double tees, columns, beams, spandrels, and wall panels. Deep double tees and shortened double tees handle the extra loading in the high load areas. These precast pieces are capable of withstanding the potentially harsh conditions of the Gulf Coast, providing peace of mind for the client — no matter what the weather may bring.