Nicholson Drive Parking Garage
Tindall
Location:
LSU
Baton Rouge, LA 70803
Schedule:
Project Start Date: 06/2017
Precast Erection Start Date: 09/2017
Precast Erection Completion Date: 12/2017
Project Completion Date: 03/2018
Cost:
Total Project Cost: $18 million
Square Footage: 247,000 SF
Cost of Precast Concrete: $6.25 million
Involved Companies
Precast Concrete Producer
Tindall Corporation
11450 Saracennia Rd
Moss Point, MS 39562
https://tindallcorp.com/
Architect
Remson, Haley, Herpin Architects
200 Government St, Suite 100
Baton Rouge, LA 70802
https://www.rhharchitects.com/
Precast Concrete Specialty Engineer
Tindall Corporation
11450 Saracennia Rd
Moss Point, MS 39562
https://tindallcorp.com/
Engineer of Record
Fox Nesbit Engineering
9100 Bluebonnet Centre Blvd
Baton Rouge, LA 70809
http://www.fox-nesbit.com/
General Contractor
Lemoine Company
15555 Airline Highway
Baton Rouge, LA 70817
http://www.lemoinecompany.com/
Background
The parking structure was designed to match the adjacent building’s design features and façade with the brick color matching other buildings throughout campus. This project highlights that parking structures do not have to be plain gray and can be designed to fit into their surroundings. It was switched from CIP to precast because of the overall cost savings which resulted from shortened construction schedule and long-term performance of precast.
Relevant Features
Cost Benefits
Schedule Benefits
Access Constraints
Working around football season
Matching surrounding buildings
“Not the look of a Parking Garage”
Innovations/Accomplishments
By using precast, over cast in place, the contractor was able to construct the project 30% - 40% faster. Through utilizing the Design-Build delivery method, Tindall was brought on-board the design team early in the process, resulting in the most efficient precast design. Tindall provided valuable input to the team on precast components from the start. Tindall was also able provide project pricing at an early stage to make sure the project design was within the owner’s budget.
Project Details
Architectural Precast –
12" Wide x 82" Deep Spandrels: 712 LF, 4,864 SF
12" Thick Architectural Panels: 723 LF, 5,365 SF
Structural Products – (double tee, columns, beams, girders, piles etc.)
12' Wide x 28" Deep Double Tees: 16,450 LF, 197,399 SF
40" Wide x 32" Deep Inverted Tees: 539 LF, 1,796 SF
08" Wide x 82" Deep Spandrels: 2,201 LF, 14,843 SF
12' Wide x 10" Thick Lite Walls: 2,592 LF, 23,980 SF
12' Wide x 12" Thick Shear Walls: 576 LF, 5,083 SF
28" x 28" Columns: 999 LF, 2,328 SF
12' Wide x 08" Thick Wall Panels: 2,208 LF, 22,210 SF
08" Wide x 60" Deep Grade Spandrels: 692 LF, 3,458 SF
12' Wide x 08" Thick Flat Slabs: 338 LF, 2,876 SF
Finishes –
Thin-set brick
Cornices and projected brick at first level
Buff colored concrete